WESTERN DISTRICT WEEKLY UPDATE FOR September 30, 2019
Kivalina Airport Erosion Control AIP 3-02-0152-2018 / Z638720000
NWABOR Title 9 Permit #N/A
Contractor Name: Brice Incorporated
Contract Award Date: June 22nd, 2018
Original Award Amount: $ 9,979,348.30
Original Contract Completion Date: October 31st, 2019
Project Engineer: Michael Freytag
Project now in closeout status and contractor has demobilized. Currently waiting for grass growth in seeded areas before final completion and cessation of project updates.
Kiana Airport Improvements AIP 3-02-0146-003-2017/Z631790000
NWABOR Title 9 Permit #109-03-17
Contractor Name: Cruz Construction, Inc.
Contract Award Date: 3/30/2018
Original Award Amount: $15,596,020.00
Original Contract Completion Date: 8/31/2020
Project Engineer: Inho Chung
Installation and Test of thaw wire completed on 10/9/19. Apron repair is being scheduled for the week of 10/21/19.
Selawik Footbridge Rehabilitation 0002269 / Z617650000
NWABOR Title 9 Permit #105-03-18
Contractor: Ridge Contracting, Inc.
Contract Award Date: February 13th, 2019
Original Contract Amount: $1,160,300.00
Contract Completion Date: May 31, 2020
Project Engineer: Scott A. Leigh, P.E.
No update. Anticipate enough ice for a detour and bridge deck work to be initiated in January
Kivalina Evacuation and School Site Access Road – Kivalina to Kisimigiuqtuq Hill 0002432/NFHWY00366
NWABOR Title 9 Permit #102-03-19
Contractor Name: ASRC Civil Construction, LLC
Contract Award Date: December 12th, 2018
Original Award Amount: $13,182,953.00
Original Contract Completion Date: October 31st, 2019
Project Engineer: Tony Cox
Production of Armor Rock and Class I/II riprap completed 10/13. Screening plant tear down in progress, followed by crusher setup and production of porous backfill. The Class A concrete mix design has been received and materials samples sent to the NRML for JMD verification. Edge Surveying is scheduled to be back on site to complete the final pit survey for the season and possibly a bathymetric survey of bridge abutment areas. The contractor has started moving equipment from the terminus pad to the causeway for winter staging. Ice has started to form in the lagoon. DOT staff scheduled to demobilize 10/18/19 with a return in early 2020 for resumption of work.